S.No. | Name of the GMC/Institute |
No. of Super specia-lity beds |
No. of ICU beds |
No.of Total beds |
No. of Ots | Project Cost (Rs.) | No of proposed PG Seats (As per Gap analysis Report) | No. of Super Speciality departments |
Status / Progress of the projects |
1 |
SCTIMST, (Trivandrum) (Kerala) |
90 | 80 | 170 | 08 | 230.00 crore (MoHFW’s Share: Rs. 120.00 Crore, DST’s share: Rs. 110.00 crore) |
25 |
05 |
In progress |
2 |
IMS BHU, (Uttar Pradesh) |
360 | 70 | 430 | 13 | 200.00 crore (MoHFW’s Share: Rs. 120.00 Crore, MoHRD’s share: Rs. 80.00 crore) |
60 | 13 |
Completed |